Period : 2000 - 2014
1 of 2
Credit : JCCBI
In-situ stress measurements on selected girders
Tecsult Inc. was awarded a contract to analyze the true stress values calculated for the bridge’s prestressed... [...]
Credit : Radio-canada
Would the Champlain Bridge be maintained or replaced?
In 2005, JCCBI commissioned Les Conseillers ADEC Inc. to carry out an economic study comparing the estimated cost of... [...]
Credit : JCCBI
Lack of funding for bridge repairs
In September 2008, the Office of the Auditor General of Canada issued a Special Examination Report on the Federal... [...]
Credit : JCCBI
Government of Canada funding announced
In 2009, the Government of Canada announced funding of $212 million over 10 years. This was increased to $239 million in 2011. That same year,... [...]
Credit : JCCBI
Champlain Bridge replacement announced
In March 2011, the BCDE consortium (BPR/CIMA/DESSAU/EGIS) submitted the detailed results of its pre-feasibility... [...]
Credit : JCCBI
Installation of the superbeam
On September 26, 2013, Buckland & Taylor Ltd. issued a report stating that even with the existing level of... [...]