fbpx

This page contains information about the work schedule for the Champlain Bridge deconstruction. You can also see how the deconstruction is progressing on our Live Work Site section, which shows images from cameras installed at strategic points at the site that will let you keep up with the work being done on Île des Sœurs.

You can also learn more about the methods to deconstruct the Champlain Bridge on this page. We will be providing more information about these methods in fall 2020. 

Deconstruction Methods

Different methods will be used depending on the section to be deconstructed and the bridge components to be taken down.

Around 65% of the work will be done from work platforms in the water that are away from residential areas.

Global Work Schedule

Work to deconstruct the Champlain Bridge will take place over 43 months until January 2024. This global schedule shows the major upcoming milestones for the different sections of the Champlain Bridge.

  • On Île des Sœurs, the deconstruction work will finish in summer 2021.

  • For Section 5 over the river to the seaway, the work will be carried out in the water and will have little impact on mobility.

  • For section 6 over the seaway, most of the work will be carried out in winter so as not to hinder marine transportation.

  • Work on Section 7 on the Brossard side will start in spring 2022.

Once the Champlain Bridge deconstruction is complete, JCCBI will begin redeveloping the shoreline.

Work Schedule

Work planned for October 2020

  • Construction of the Île des Sœurs jetty

  • Construction of the Brossard jetty

  • Preparatory work for the shoreline deconstruction on Île des Sœurs

 

Note that the schedule may change depending on how the work progresses and on weather conditions.

WORK IN PROGRESS – Construction of temporary piers

Construction of a temporary pier has begun on Île des Sœurs and will continue throughout winter 2020-2021 with the creation of two fish migration corridors.

JCCBI is also carrying out projects to compensate for fish habitat that may be lost due to the construction of the piers. These projects nevertheless represent a gain for the environment, as the construction-site impacts are temporary, while the positives of the compensation projects will be permanent!

The installation of the pier on the Brossard side (Phase 1) has begun a few weeks ago, and the widening of the pier (Phase 2) will start in spring 2021. Finally, a third pier will be built on the St. Lawrence Seaway dike (near the Champlain Bridge Estacade) in 2021. 

All of these piers will be used to take down structural bridge components along the shoreline where barges cannot be used due to the shallow water depth.

Upcoming Work

In the Île des Sœurs sector, NHSL will start deconstructing the shoreline spans and piers in October, and this work will last for 9 months. Mitigation measures will be deployed to minimize the impact of truck traffic, and trucks will use predetermined routes to avoid residential neighbourhoods.

Sound level meters and air quality measurement stations will also be installed to ensure compliance with standards. A short-term partial traffic hindrance will be set up on Île-des-Sœurs Boulevard. The details of this traffic hindrance will be issued shortly.

 

This work may generate:

  • Noise due to the deconstruction work and the off-site transportation of materials.

  • Dust emissions.

  • Occasional local traffic hindrances.

 

JCCBI will install:

  • Sound level metres at the work site to ensure compliance with standards.

  • Air quality monitoring stations to ensure compliance with standards.

REVIEW OF WORK ON ÎLE DES SOEURS

Deconstruction of the abutment and the two spans above René-Lévesque Boulevard on Île des Sœurs began in mid-August and finished at the end of September. René-Lévesque Boulevard had to be closed for two weeks during the work, but a bicycle and pedestrian corridor was maintained thanks to a shuttle service.

To uphold peace and quiet for residents, sound level meters and air quality measurement stations were installed at different spots around the work site. None of the allowed thresholds were exceeded, and no citizen complaints were received.

Shoreline deconstruction (Île des Sœurs and Brossard)

Method: Traditional mechanical deconstruction on land

Work steps:

  • Preparatory work

    • Dismantling of components (overhead signage, lights, etc.)

    • Components removed for the Research and Development program

    • Removal of reinforcements 

 

  • Installation of temporary supports 

  • Deconstruction of the spans and piers

  • Disposal and removal of debris

  • Restoration of the area

Deconstruction over the river

Method: Deconstruction from a platform on a catamaran barge

Work steps: 

  • Preparatory work

    • Dismantling of components (overhead signage, lights, etc.)

    • Components removed for the Research and Development program

    • Removal of reinforcements 

 

  • Span recovered with a system of platforms attached to lifting towers installed on a catamaran barge

  • Deconstruction of the span on the catamaran barge

  • Barge-based mechanical deconstruction of the piers and footings above and below the water level, from top to bottom

  • Debris disposal by barge

Deconstruction of the steel structure over the seaway

 Methods used to remove the steel structure:

  • The suspended span will be placed on a barge with strand jacks and dismantled on the barge piece by piece.

  • The cantilever sections and anchor spans will be taken apart piece by piece using a crane set up on temporary jetties.

  • The piers will be mechanically deconstructed with high-capacity excavators.

Research and Development

Different structural components such as concrete panels, bearings, and girders were also given to the groups of the Research and Development program that is going on during the original Champlain Bridge deconstruction project.