fbpx

Media Centre

The Corporation makes sure that some of Montreal’s most important and significant infrastructure remains safe, fully functional and aesthetically pleasing. We strive to maintain open and transparent dialogue with the media and the public.

Press releases

September 2021

June 2021

May 2021

 

April 2021

February 2021

October 2020

Août 2020

July 2020

June 2020

May 2020

April 2020

March 2020

February 2020

January 2020

December 2019

November 2019

October 2019

 

Latest news

Champlain Bridge deconstruction | R&D project – Assessment of Corrosion and Evaluation of the Degree and Distribution of Corrosion on the Response of Girders - This month’s featured project by McGill University is progressing very well.  This research project will provide information on the performance of the girders and some of the repair techniques used on the Champlain Bridge. The project is aimed to study the initiation of the corrosion in the cables and the sensitivity of the girders performance to the […]
Compensation project in Saint-Ignace-de-Loyola: positive, permanent impacts for wildlife - The construction of three temporary jetties in the St. Lawrence to deconstruct the Champlain Bridge has of course interfered with the natural fish habitat in the river. This is why JCCBI is implementing a compensation project in collaboration with Nature Conservancy of Canada (NCC) to develop a piece of agricultural land along the St. Lawrence River in […]
Original Champlain Bridge | JCCBI wins circular initiative award for the Material Reuse Competition - The Prix initiatives circulaires was held on October 7, 2021. Our teams were very proud to learn that the Canada-wide Champlain Bridge Material Reuse Competition won the award in the public organization category of the Prix initiatives circulaires, an event organized by Québec Circulaire and RECYQ-QUÉBEC. The deconstruction of the Champlain Bridge will result in […]
New deconstruction method for the bridge piers and footings - A new phase of the bridge deconstruction that will begin in the coming weeks will require a new deconstruction method. The teams will begin work to remove the bridge piers (or its “legs”) and the footings that sit under water.    This operation will be carried out with specialized excavators on barges that will serve […]
The “River Giant” in action on the St. Lawrence River - The first span of the original Champlain Bridge over the river, was successfully taken down in early July. About ten spans have been removed so far. This mega catamaran barge that was custom-built by a multitude of Quebec, American and European engineering firms has three main functions: With an accuracy of within 2 mm, it lifts […]
PRESS RELEASE | Jacques Cartier Bridge multipurpose path and sidewalk: extended hours this winter - The Jacques Cartier and Champlain Bridges Incorporated (JCCBI) is pleased to announce that active mobility enthusiasts will have longer hours to use the Jacques Cartier Bridge’s multipurpose path and sidewalk this winter. Weather permitting, people will be able to use the path and sidewalk 7 days a week, between 5:00 a.m. and 10:30 p.m., which […]
JCCBI honoured at AFG Quebec’s 2021 consulting engineering grand awards - The 19th edition of the Grands Prix du génie-conseil québécois 2021 were held on Tuesday, September 21. We are very proud to announce that our teams, together with CIMA+, which worked on modernizing the systems of the Melocheville Tunnel, won the award in the Telecommunications and New Technologies category at this event. For this project, […]
Jacques Cartier Bridge | “Half-masting” for the illumination - On August 2, 2021, JCCBI modified the procedure for “half-masting” the illumination of the Jacques Cartier Bridge. Being a federal Crown corporation, JCCBI ensures that the illumination of the Jacques Cartier Bridge follows the notices of half-masting of the Canadian flag, issued by Canadian Heritage, normally for a period of 24 hours. The annual illumination […]
A spectacular operation: The “River Giant” to dismantle 30 spans from over the river - At the end of June, the “River Giant” began dismantling the 30 spans of the original Champlain Bridge in the seaway sector using a unique platform system mounted on six lifting towers installed on a “mega barge.” Photo: The “River Giant” that dismantles the spans When extended to their maximum height, these towers lift the […]

 

 


Information request

All requests for access to information are processed in accordance with the Access to Information Act and the Privacy Act. Consult Info Source about the specific steps required to access information.