WORK COMPLETED | Honoré Mercier Bridge – Complete closure of the access ramp for the Hwy. 138 East, toward Montreal, from July 17 to 29 | PJCCI
WORK COMPLETED | Honoré Mercier Bridge – Complete closure of the access ramp for the Hwy. 138 East, toward Montreal, from July 17 to 29
July 12, 2021 Honoré Mercier Bridge

Updated [2021-07-24]

 

WORK COMPLETED  in advance – access ramp for the Hwy. 138 East open toward Montréal

TRUCKS : no more prohibited toward Montéal 

 


 

MAJOR WORK BLITZ of 12 days 

  • From Saturday, July 17, 10 p.m., to Thursday, July 29, 10 p.m.
  • Complete closure of the access ramp for the Hwy. 138 East, toward Montreal.

TRUCKS: All access ramps from the south shore to Montreal – Hwy. 138 East (leveling and paving work) and Hwy. 132 West (detour for cars an public transports) – are prohibited to trucks in order to streamline the trafic.


 

DETOURS:

  • Cars: Detour via Hwy.132 E/Hwy.30/Hwy.15 La Prairie, u-turn on Old Malone, access ramp to the Bridge toward Montreal (see map).
  • Public transports: Detour via Hwy.132 E/Hwy.30/Hwy.15 La Prairie, follow the priority access on Old Malone, access ramp to the Bridge toward Montreal (see map).
  • Trucks: Crossings of the Honoré Mercier Bridge from the south shore to Montreal prohibited to trucks, please use the other bridges of the south shore.

For leveling and paving work.