-2015
-2025
2015
2025

Period : 2015 - 2025

Distribution of 4,000 rivets to the population

Back

In September 2023, JCCBI wanted to mark the end of the deconstruction of the original Champlain Bridge by offering the public the opportunity to obtain a rivet taken from its steel structure likely the most visible and significant portion for people.

Approximately 4,000 rivets were given out to the public at two events held over the weekend on September 9 and 10 in Brossard and on Île des Sœurs.

The event was a great success!

Rivets distributed to residents in Brossard

Credit: JCCBI
Rivets distributed to residents in Brossard.

Rivets distributed to residents on Île des Soeurs

Credit: JCCBI
Rivets distributed to residents on Île des Soeurs.

Deconstruction of the last pier footings and removal of the jetties

By fall 2023, the remaining operations consisted of finalizing the removal of five concrete pier footings on the temporary St. Lawrence Seaway dike and Brossard jetties. While the footings were being deconstructed, the temporary jetties were gradually removed, and the site was restored by NHSL.

Removal of the remaining footings on the temporary Brossard jetty

Credit: JCCBI
Removal of the remaining footings on the temporary Brossard jetty.

End of the major project

In November 2023, the project was completed two months ahead of schedule and within the initial budget of $225.7 million, plus direct costs related to COVID-19 management. Only three complaints were recorded during the 41 months of work. JCCBI achieved its goal to successfully deconstruct the historic original Champlain Bridge through in-depth planning to minimize the impact on the environment and the public, and to promote the recycling and reuse of materials.

The deconstruction of the original Champlain Bridge ended in November 2023

Credit: JCCBI
The deconstruction of the original Champlain Bridge ended in November 2023.

Narration
Go to top