Dear Neighbour,
The Jacques Cartier and Champlain Bridges Incorporated (JCCBI) is continuing its program to reinforce the Jacques Cartier Bridge and its approach structures in order to extend the service life of the bridge.
From April until November 2018, JCCBI will be conducting repairs on two viaducts located at the south approach of the Jacques Cartier Bridge. To minimize inconveniences from the work, JCCBI has planned
three major work blitzes.
The first two blitzes will be on the off-ramp viaduct of the Jacques Cartier Bridge to Saint-Laurent Street, Hwy. 20 and Hwy. 132. This work will be done the weekends of Friday, April 20 to Monday, April 23 and
Friday, May 4 to Monday, May 7, 2018.
Friday, April 20 to Monday, April 23 and Friday, May 4 to Monday, May 7
Another major work blitz has been scheduled for the end of May 2018 for repair work on the Saint-Laurent Street / Hwy. 134 on-ramp viaduct to the Jacques Cartier Bridge toward Montreal.
Note that this work could be postponed to a later date or the work plan could be changed because of unsuitable weather conditions.
Stay informed by subscribing to our various communication tools:
If you have questions or comments, please contact us by filling the request form on the Contact use page.