fbpx

Nautical traffic under Champlain Bridge: St. Lawrence River Section : From August 16

The Jacques Cartier and Champlain Bridges Incorporated (JCCBI) wishes to advise boat operators that new signage is in place from August 16 until further notice, under the Champlain Bridge and Champlain Bridge Ice Control Structure. The corridor is moved to the east (between 15W and 16W of Champlain Bridge). Subsequently, this corridor will be moved ...
16 August 2016   ·


Honoré Mercier Bridge major deck replacement work : work progress August, 11

The work still progressing well. Here is a table which will be broadcast once a week over the next week, to allow you to see the progress of the work. ...
11 August 2016   ·


Honoré Mercier Bridge major deck replacement work : work progress August, 4

The work still progressing well. Here is a table which will be broadcast once a week over the next week, to allow you to see the progress of the work. ...
4 August 2016   ·