Jacques Cartier Bridge: Complete night closures February 13, 20 and 27

15 February 2017

img_avis_travaux_JC

ADDITION OF A COMPLETE CLOSURE

Please note that due to favorable weather conditions, the Jacques Cartier Bridge will be completely closed on Friday, February 24, for the installation of light fixtures over the traffic lanes.

 

Details of the closures

Week of February 20

  • Complete closure of the bridge, in both directions, from Monday, February 20, to Tuesday, February 21, from Tuesday, February 21, to Wednesday, February 22 and from Wednesday, February 22, to Thursday, February 23, from midnight to 4 a.m.
  • Complete closure of the bridge, in both directions, from Friday, February 24 to Saturday, February 25, from midnight to 4 a.m. Lanes will start closing at 11:30 p.m. An access will be maintained for emergency services.

Week of February 27

  • Complete closure of the bridge, in both directions, from Monday, February 27, to Tuesday, February 28, from Tuesday, February 28, to Wednesday, March 1st and from Wednesday, March 1st, to Thursday, March 2, from midnight to 4 a.m.

 

The goal of these closures is to ensure safety for users and workers during the work. JCCBI recommends that road users judiciously plan their travels ahead.

Note that this work could be postponed because of unsuitable weather conditions. Additional overnight closures are to be expected this winter. Follow our Twitter feed @pontJCBridge, subscribe to our SMS alerts  for more information.